Question
A dam wall must hold back water. At one location the water is deep. Engineers make the lower part of the wall much thicker than the upper part.
Total: 4 marks
(a) Find the gauge pressure at the bottom of the water column. (1 mark)
(b) Find the gauge pressure halfway down, at depth . (1 mark)
(c) Explain why the lower part of the dam needs greater strength. (1 mark)
(d) Does the pressure at a point depend on the total length of the reservoir? Explain briefly. (1 mark)